Implementation Tips For Owner Contingency or Allowances for Commercial Construction Contracts

There is a requirement to tie out the AIA Pay Applications to each of the Subcontract trade contracts and also track the $$ budgeted as an 'Owner Contingency' as the $$ are re-allocated during the course of construction.

Our recommendation is to set up an Initial Change Order in Sage Construction Management to track the contingency $$ as separate line items with negative values. This Change Order is a tracking mechanism only and will NOT be billed on the pay apps. It is designed purely as a means to show how the contingency $$ were spent and allocated to the individual Change Orders that serve as the basis to create subsequent Subcontractor Change Orders.

Example Project Screen shots are shown below.

Step 1: ORIGINAL PRIME CONTRACT with $200,000 Owner Allowance




Step 2 - CREATION of CHANGE ORDER 000 to track Owner Allowance � Line item for each Reallocation




Step 3 - CREATION of CHANGE ORDER 001 and Subsequent Creation of SCO based on this CO






Step 4 - CREATION of CHANGE ORDER 002 and Subsequent Creation of SCO based on this CO






Step 5 - CREATION of CHANGE ORDER 003 and Subsequent Creation of SCO based on this CO � No Effect on Owner Contingency

CO 003 shown below does not pertain to Contingencies so therefore it is not referenced in CO 000.






Step 6 - AIA Pay Application - See Effect on Owner Contingency and Each of the affected Trades (Revised Contract Amts tie out to each of the Subcontract current values and Owner Allowance has been reduced by -$70,000)